Andrew & Rebecca's Ascot 24 build with Metricon
Sunday 18 November 2012
A few bricks away from LOCK UP!
›
Things have been moving rather quickly since the site was cut a month ago, the roof, water connections to bathrooms/kitchen/laundry have bee...
Wednesday 31 October 2012
Delays
›
Sadly the rain arrived on Thursday which resulted in a delay to our frame construction. Our site manager hopes the tradies will be able to s...
Tuesday 30 October 2012
Colour selections- Laundry and Bathrooms
›
Laundry- Rock salt square edge for bench top Habitat matt finish for cupboards Bathroom & ensuite- Endula macassar square ABS edging...
Colour selections
›
Kitchen Top cupboards and rear island bench - Seductive Limba matt finish All other draws - Pumice gloss finish Stone bench top - expres...
Floor plan & Facade
›
Chateau facade.
30th October- Frame and Window delivery
›
Frame and Windows were delivered today, we chose Dune for our window frames. They look great. The frame should be started tomorrow.
Stage 1 pictures
›
›